| Idaho Power Integrated Resource Plan (IRP) |
 |
|
 |
|
|
The Commission is reviewing Idaho Power’s new Integrated Resource Plan (IRP).
Utilities regulated by the Commission must file IRPs every two years. The plan identifies projected growth and what resources the utility wants in order to serve its customers. One element of Idaho Power’s IRP is a proposal for a new transmission line.
If a new route is approved by the Oregon Energy Facility Siting Council the Commission may also be asked to issue a Certificate of Public Convenience and Necessity (CPCN) for the construction of overhead transmission lines.
A CPCN would permit land to be condemned as a last recourse to complete the transmission project.
If Idaho Power makes this request, the OPUC will issue notices and hold public hearings.
View Filing
|
|
|
|